A136 Highlight Tower from the DIM group of companies is the first in Ukraine to undergo an audit from the largest international investment consulting and property management company CBRE Ukraine
Today, with official updates from the international consulting company CBRE Ukraine, construction on the A136 Highlight Tower complex is progressing rapidly. More than half of all work is already underway, and if this pace is maintained, all ongoing work on the Maidan will be completed by the end of 2024.
It indicates that, based on the results of a visual inspection of the progress of the construction work and review of the given schedule, the monolithic work has been completed, the entire complex has been completed, and the drying process has been completed. . Rashta works in the Vikonan complex in half.
The company also emphasizes that the end date for the completion of business activities in the 4th quarter of 2024 is not conservative, but rather optimistic. According to this statement, the lines are completely true, and increasing the speed of engineering work can accelerate the completion of life.
function gallery3373118() {
$.get(‘//’ + window.location.host + ‘/ajax/module.aspx?spm_id=520&id=3373118&lang=2&IsAjax=true’, function (data) { $(‘#gii3373118’).html(data); });
}
gallery3373118();
“The most important thing for consumers is the speed of everyday life. We will be effective, that’s what they believe, not only a thousand months showing the picture of the course of daily life, but they introduce a quarterly audit system for an international company– revealing junior partner of DIM group of companies Arseniy Nasikovsky,- CBRE Ukraine says that at the time of inspection the booths were 54% ready. In my opinion, we have a very large number, and we have completely covered all types of work necessary to complete our daily life. I would like to point out that the most important stages are such as monolithic work, single-piece masonry, roof varnishing, weaving, either the last stage or the last stage. In particular, the main emphasis is on the façade and interior robots“
The DIM group of companies, from the beginning of a large-scale invasion, did not realize the fact that allowed them to take a leadership position in the market in 2024. So, from the 200 thousand square meters put into operation in Kiev in the first three months of production, the developer himself made 120 thousand. The company plans, at a minimum, to run more of the same before the end of life.
You can familiarize yourself with the international auditor CBRE by following the instructions.
Source: korrespondent

I’m Liza Grey, an experienced news writer and author at the Buna Times. I specialize in writing about economic issues, with a focus on uncovering stories that have a positive impact on society. With over seven years of experience in the news industry, I am highly knowledgeable about current events and the ways in which they affect our daily lives.