Power supply of ZNPP has been restored – Energoatom

Image: Getty Images

Two days after the plant was disconnected from the Ukrainian power grid, NPP employees repaired the damaged line.

Ukrainian specialists repaired and installed a high-voltage communication line of 750 kV Zaporizhzhya NPP – Dneprovskaya. On Sunday, October 9, the press service of Energoatom reported.

“After nearly two days of operation of emergency pumps for cooling the cores of nuclear power plant reactors powered by diesel generators, operational personnel are restoring normal procedures for supplying the plant’s own needs from Ukrainian energy system,” the message said.

It was noted that the radiation background at the ZNPP site and the adjacent territory did not change and was within the normal range.

It will be remembered that on the night of October 8, the aforementioned high voltage line was damaged as a result of Russian shelling, which led to a complete blackout of the station.

theft of NPP. What is happening at Energodar?

News from Correspondent.net on Telegram. Subscribe to our channel Athletistic

Source: korrespondent

- A word from our sponsors -

Most Popular

LEAVE A REPLY

Please enter your comment!
Please enter your name here

More from Author

- A word from our sponsors -

Read Now

Rossius army is angry, seeing the appearance

The Russian army is trying to create a general impression of the ceasefire, but does not leave some attempts to move. .in_text_content_22 {width: 300px; Height: 600px; } @Media (min-width: 600px) {.in_text_content_22 {width: 580px; Height: 400px; }} .Adsbygoogle {Touch-Action: Manipulation; } This...

Mother and Sin settled in a circle after three Plenid flights (video)

Mother and son - the grapes of Margarita and Ruslan - unexpectedly met at today's exchange after three years of captivity after Azovstal left in Maripul. .in_text_content_22 {width: 300px; Height: 600px; } @Media (min-width: 600px) {.in_text_content_22 {width: 580px; Height: 400px; }} .Adsbygoogle {Touch-Action: Manipulation;...

In Bell House, they were a goat goat in a scandal with a signal date

US Secretary of Defense Pitt Hegset will be released using data leakage. .in_text_content_22 {width: 300px; Height: 600px; } @Media (min-width: 600px) {.in_text_content_22 {width: 580px; Height: 400px; }} .Adsbygoogle {Touch-Action: Manipulation; } The politician writes about this. The head...